Change order requests (CORs)

A COR is used for tracking requests for changes to the original contract between the general contractor and the project owner. You can link multiple potential change orders (PCOs) to a COR.

On the Change Order Request tab, the banner displays:

  • Amount: The total revenue amount from the linked PCOs.
  • Days: The total number of approved days from the Information panel.

The Change Order Requests module displays the requested days for unlocked records and the approved days for locked records.